Builder Notice of Insufficient Progress. If the actual progress of the Work in comparison to the Project Schedule indicates that the Work is not substantially on schedule as set out in the Project Schedule and that the completion of the Vessel by its Delivery Date is in jeopardy, then Builder shall promptly notify Owner and provide a proposed revision to the Project Schedule with such adjustments to sequencing or allocation of resources as may be commercially reasonable to overcome such delays and complete the Vessel by the Delivery Date or as soon thereafter as reasonably practicable.
If the actual progress of the Work in comparison to the Project Schedule indicates that the Work is not substantially on schedule as set out in the Project Schedule and that the completion of the Vessel by the Delivery Date is in jeopardy, then Builder shall promptly notify Owner and provide a proposed revision to the Project Schedule with such adjustments to sequencing or allocation of resources as may be necessary to overcome such delays and complete the Vessel on time. If Builder fails to provide such notice and take such action, then Owner shall notify Builder of its concerns (without prejudice to any of Owner’s other rights pursuant to this Agreement). In such case, within fifteen (15) Working Days thereafter, Builder shall provide to Owner a revised Project Schedule showing such adjustments as necessary to complete the Vessel on time.
Builder Revision of Project Schedule. In such case, within thereafter, Builder shall provide to Owner a revised Project Schedule showing such adjustments as necessary to complete the Vessel by the Delivery Date or as soon thereafter as reasonably practicable.
AllDrafts is a cloud-based editor designed specifically for contracts. With automatic formatting, a massive clause library, smart redaction, and insanely easy templates, it’s a welcome change from Word.
And AllDrafts generates clean Word and PDF files from any draft.