Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Architectural / Structural DEMOLITION Demo Interior Floors, Walls, & Ceilings (allow) 20,000 sf $ 5.00 $ 100,000 Demo Exterior Tilt up Concrete Exterior 226 sf $ 22.50 $ 5,085 Demo Concrete Floor incl Sawcut for Mezz Ftgs 115 cy $ 295.00 $ 33,802 Demo Concrete Floor incl Sawcut for US Piping Sawcutting of Slab on Grade for Underslab piping 822 lf $ 5.00 $ 37,800 Backfill and compact soil 232 cy $ 27.00 $ 6,967 Remove concrete debris by hand 30 cy $ 175.00 $ 5,328 Temporary Partition Allowance (Plastic along Mezzanine Border 5,000 sf $ 2.00 $ 10,000 Load, Haul & Dispose of Debris 525 cy $ 85.00 $ 44,662 Demolition Total $ 243,644 SUBSTRUCTURE Foundation (5' spread footing + 3' grade wall) 53 cy $ 630.00 $ 33,600 Slab on Grade for Utility Building 1,600 sf $ 9.00 $ 14,400 Infill Ex Slab on Grade (6" concrete + 6" granular fill) 7,832 sf $ 13.50 $ 105,725 Interior Column Pads 305 cy $ 540.00 $ 164,588 Dowel for Mezz Column Pads - (1) every 12" 3,300 ea $ 22.50 $ 74,250 Doweling for Trench Drains - (1) every 12" 822 ea $ 22.50 $ 18,495 Allowance for Equipment Pads 1 ls $ 18,000.00 $ 18,000 Elevator Pit 1 ea $ 10,000.00 $ 10,000 Substructure Total $ 439,058 SUPERSTRUCTURE Elevated Slabs (metal deck + 5" concrete) 38,000 sf $ 10.80 $ 410,400 Elevated Slab Steel Framing (11#/sf) 209 tons $ 4,590.00 $ 959,310 Equipment Galv Carbon Steel Grating for RO Equipment 200 sf $ 16.20 $ 3,240 Equipment Platform Steel Framing (10#/sf) 2 tons $ 4,950.00 $ 7,425 Platform Handrail 40 lf $ 225.00 $ 9,000 Stairs 15 risers $ 500.00 $ 7,500 Stanchions on Mezzanine & New Chillers / Boiler 40 ea $ 2,000.00 $ 80,000 Pipe Carrier up side of bldg 0.75 tons $ 6,500.00 $ 4,875 Epoxy Paint Structural Steel (in Open Area) 11,754 sf $ 3.15 $ 37,024 Elevator Steel 1 ls $ 10,000.00 $ 10,000 Pre-fab Pan Fill Stairs incl Handrails 64 riser $ 630.00 $ 40,320 Superstructure Toatal $ 1,569,094 EXTERIOR CLOSURE Tilt up Concrete Wall Penetrations 1 ls $ 20,000.00 $ 20,000 New Metal Panel Infills 226 sf $ 50.00 $ 11,300 Exterior Single Doors 4 ea $ 2,000.00 $ 8,000 Rollup Doors, Dock Pads/Seals 2 ea $ 5,850.00 $ 11,700 Exterior Skin Consultant 1 ls $ 10,000.00 $ 10,000 Louvers 200 sf $ 67.50 $ 13,500 Exterior Closure Total $ 74,500 ROOFING Penetrations thru Roof 1 ls $ 20,000.00 $ 20,000 Tie-In to Existing Building 125 lf $ 58.50 $ 7,313 Roofing Total $ 27,313 INTERIOR CONSTRUCTION Walls Walls Ext - GWB -0/1, on 7/8" Mtl Studs Batt Insulation 19,093 sf $ 5.75 $ 109,785 Walls Ext - GWB -0/1, on 3 5/8" Mtl Studs 2,773 sf $ 6.30 $ 17,470 Walls - GWB - 1/1 on 6" " Mtl Studs 10,697 sf $ 9.00 $ 96,273

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Architectural / Structural 24" x 24" Wall Mount Pass-Thru 6 ea $ 15,000.00 $ 90,000 Stainless Steel Benches 30 lf $ 1,000.00 $ 30,000 Gown Room Bench 45 lf $ 80.00 $ 3,600 Misc. Stainless Steel Accessories 1 ls $ 10,000.00 $ 10,000 Operating Tables 2 ea By Owner Audio - Visual Displays Equipment - allowance 5 rms $ 5,000.00 $ 25,000 dock Door Levelers 2 ea $ 7,200.00 $ 14,400 Millwork Casework - Painted Metal Cabinet w/ Epoxy Resin Top 26 lf $ 600.00 $ 15,600 Laminated Bathroom Countertop 25 lf $ 150.00 $ 3,750 Kitchen Counter & Cabinets - Laminated Top 17 lf $ 500.00 $ 8,500 Reception Desk 15 lf $ 1,500.00 $ 22,500 Mailroom / Copy Room - Cubbies, Storage, Counters 1 ls $ 20,000.00 $ 20,000 Cubicles 48 ea Owner Office Desks, chairs, file cabinets 2 ea Owner Conference Room Table & Chairs 7 ea Owner Privacy Room Furniture 2 ea Owner Break Room Table & Chairs 1 ls Owner Special Construction Total $ 2,533,350 CONVEYING SYSTEMS Elevator Freight, 2 story 1 ea $ 150,000 $ 150,000 Conveying Systems Total $ 150,000 Architectural / Structural Total $ 7,045,405 $ 7,045,405

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Building & Process Electrical Nitrogen monitoring 1 allow $ 11,175.00 $ 11,175 Card Readers 47,874 sf $ 0.75 $ 35,666 Lightning Protection 37,334 sf $ 0.75 $ 27,814 Security Cameras, IT Equipment & Racking by Owner Grounding System for New Mechanical Level 37,334 sf $ 3.73 $ 139,069 Phones Jacks & Public Address System 68,432 sf $ 2.24 $ 152,946 $ — $ 924,510 MECHANICAL EQUIPMENT FEEDS $ — 480V, 3Ph 50 ea $ 2,607.50 $ 130,375 208V/120V, 1Ph 60 ea $ 1,117.50 $ 67,050 $ — $ 197,425 "***" $ — ''***'' 28 ea $ 3,725.00 $ 104,300 ''***'' 102 ea $ 1,117.50 $ 113,985 $ 218,285 Electrical Total $ 5,721,100 $ 5,721,100

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Building HVAC / Utilities HVAC Dryside Makeup Air Unit (1x thru) 17,000 cfm $ 6.00 $ 102,000 Semi - Custom AHU Quoted 1 ea $ 487,200.00 $ 487,200 w/o Economizers & Heat Recovery 1 ls $ 450,000.00 Excluded Grade C AHU (recirc) 1,500 cfm 1 ea $ — included Grade C AHU (recirc) 3,000 cfm 1 ea $ — included Grade C AHU (recirc) 4,500 cfm 1 ea $ — included Grade D AHU (recirc) 15,000 cfm 1 ea $ — included Grade D AHU (recirc) 12,000 cfm 1 ea $ — included Grade D AHU (recirc) 20,000 cfm 1 ea $ — included Office RTU 35,000 cfm $ — existing Board Room RTU - 3 tons / 1,200 cfm 1 ea $ 4,000.00 $ 4,000 Office RTU - 3 tons / 1,200 cfm 1 ea $ 4,000.00 $ 4,000 Office RTU - 3 tons / 1,200 cfm 1 ea $ 4,000.00 $ 4,000 Cabinet Unit Heater, 10 MBH 3 ea $ 1,200.00 $ 3,600 Fan Coil Unit (CHW cooling & HW Reheat) 34,325 cfm total 10 ea $ 4,500.00 $ 45,000 Warehouse Fan Coil Unit (CHW cooling & HW Reheat) 34,325 14 ea $ 4,500.00 $ 63,000 cfm total Mech Room Fan Coil Unit (CHW cooling) 2 ea $ 2,500.00 $ 5,000 Fan Coil Unit (CHW cooling) 1,500 cfm 1 ea $ 2,500.00 $ 2,500 DX Split Systems for Electrical, Telecom and Server Rooms (4) 1 ls $ 75,000.00 $ 75,000 Exhaust Fan 3,550 cfm $ 1.25 $ 4,438 Exhaust Fan 1,900 cfm $ 1.30 $ 2,470 Exhaust Fan 1,950 cfm $ 1.30 $ 2,535 Exhaust Fan 2,850 cfm $ 1.30 $ 3,705 Exhaust Fan 900 cfm $ 2.00 $ 1,800 Exhaust Fan 150 cfm $ 3.25 $ 488 VAV's w. phoenix valve & HW reheat 15 ea $ 4,500.00 $ 67,500 CV's w. phoenix valve 15 ea $ 3,000.00 $ 45,000 RHCs, hot water, duct-mounted 25 ea $ 1,750.00 $ 43,750 “***” “***” “***” “***” Flexiduct 1 ls $ 2,500.00 $ 2,500 Air & Water balance 1 ls $ 50,000.00 $ 50,000 Rigging 1 ls $ 50,000.00 $ 50,000 Galv Ductwork with grills and volume dampers. Includes 94,480 lb $ 9.00 $ 850,320 Rework of Existing Office Ductwork (50% new duct.) SS Duct for LWR 9,448 lb w/ Prefab quote, if required SS Duct for Biosafety Cabinets 1 ls $ — not exhausted Economizer Ductwork 600 lbs $ — Excluded Duct Insulation - Wrapped 47,240 sf $ 4.00 $ 188,960 HEPA Filters - ducted disposable 122 ea $ 1,500.00 $ 183,000 Fan Filter HEPAs 1 ea w/ Clean Rooms HEPA Filter Certification 123 ea $ 150.00 $ 18,450 Registers, Diffusers 71 ea $ 150.00 $ 10,650 Louvers allowance 300 sf $ 75.00 $ 22,500 Roof Curbs 12 ea $ 1,750.00 $ 21,000 Wet Side Chillers, Air Cooled, (3) 750 tons $ 500.00 $ 375,000 CHW Pump Skid - (2) 1,200 GPM pumps 40 HP ea, air separator, chemical feed vessel, expansion vessel, 1000 tons 1 ls $ 95,000.00 $ 95,000

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Process "***" "***" 1 ls $ 125,000 $ 125,000 "***" 1 ls $ 200,000 $ 200,000 "***" 18 ea $ — by others "***" 79 ea $ — by others "***" 4 ea $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 6 ea $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 1 ls $ — by others "***" 2 ea $ — by others "***" 4 ea $ — by others "***" 1 ls $ — by others "***" 1 ls $ 8,125 $ 8,125 "***" 1 ls $ 9,994 $ 9,994 Process Equipment Total $ 343,119 PROCESS UTILITY EQUIPMENT "***" 1 ls $ 75,000 $ 75,000 "***" 1 ls $ 70,000 $ 70,000 "***" 4 ea $ 150,000 by Owners "***" 1 ls $ — by others "***" 1 ls $ 3,625 $ 3,625 "***" 1 ls $ 4,350 $ 4,350 Process Utility Equipment Total $ 152,975 EQUIPMENT INSTALLATION Process Equipment Installation 1 ls $ 57,500 $ 57,500 Process Utility Equipment Installation 1 ls $ 74,500 $ 74,500 Process Installation Total $ 132,000 PIPING & VALVING PIPING MAINS Compressed Air Piping .5" copper 480 lf $ 63.00 $ 30,240 Nitrogen 1" copper 354 lf $ 84.00 $ 29,736 Soft Water 2" 316L pipe 35 lf $ 192.00 $ 6,720 RO/DI Water (loop)1 1/ 2" 316L Pipe 600 lf $ 150.00 $ 90,000 LOCAL PIPING Compressed Air Piping .5" copper 180 lf $ 84.00 $ 15,120 CDA to process suites 150 lf $ 84.00 $ 12,600 Nitrogen .75" copper (assume 10 points of use) 300 lf $ 91.00 $ 27,300 RO/DI Water (loop)1 1/ 2" 316L Pipe 100 lf $ 260.00 $ 26,000 Passivation 1,685 lf $ 6.00 $ 10,110 Process Utility & Process Piping Total $ 247,826 INSTRUMENTATION & CONTROLS EMS System EMS - differential pressure sensors 84 pts $ 2,200.00 $ 184,800

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Sitework - SITEWORK Axogen Sitework Allowance for Roads Drainage, Paving Sidewalls and Fencing 1 ls $ 600,000.00 $ 600,000 Demo Existing Paving incl above Soil Boring, Report & Survey by Owner Exterior Painting Allowance incl above Building Signage incl above Patch/Repair Asphalt Paving incl above New 6" Concrete Sidewalk incl above Misc. Site Grading, Clearing incl above Landscaping Allowance incl above Sitework Total $ 600,000 Underground Mechanical Total $ — UNDERGROUND PLUMBING Sanitary Sewer - New Line, Manhole and Tie-in 1 ls $ 15,000.00 $ 15,000 Domestic Water - Allow 200 lf $ 150.00 $ 30,000 Natural gas 200 lf $ 112.50 $ 22,500 Storm Drainage Existing Underground Plumbing Total $ 67,500 UNDERGROUND FIRE PROTECTION Fire Protection Loop (incl hydrants) lf $ 90.00 Excluded Allowance for Fire Pump with Shed ls $ 26,250 Excluded PIV Valve 1 ea $ 10,000 $ 10,000 Fire Protection Line 200 lf $ 150.00 $ 30,000 Underground Fire Protection Total $ 40,000 UNDERGROUND ELECTRICAL PVC Conduits - 2500A , 34.5KV assume (4) 4' dia conduit 1,288 lf $ 105.00 $ 135,240 Concrete Encasement 1/2 cy / lf 175 cy $ 150.00 $ 26,250 Cabling $ - By Utility Co. Demo Existing Paving incl above Patch/Repair Asphalt Paving 389 sy $ 60.00 $ 23,333 Excav/Backfill 311 cy $ 37.50 $ 11,667 Underground Electrical Total $ 196,490 Sitework Total $ 903,990 $ 903,990

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Building & Process Electrical ELECTRICAL DEMOLITION & TEMPORARY REQUIREMENTS Temporary Power & Lights 1 ls $ 22,000 $ 22,000 Start-up and Testing 1 ea $ 10,900 $ 10,900 Electrical Permit 1 ea $ 10,000.00 $ 10,000 $ 42,900 MAJOR EQUIPMENT Transformer - 2500kVA, 480Y/277V 1 ea $ 110,000.00 by Utility Co. Power Feeder 60 lf $ 1,415.50 $ 84,930 ATS 3000A , 480Y/277V 1 ea $ 65,000 $ 65,000 Feeder to MCSWB - 3000A, 3Ph, 4W 30 lf $ 1,415.50 $ 42,465 MCSWB - 3000A, 3Ph, 4W 1 ea $ 275,000.00 $ 275,000 Feeders Chillers – 3ea. X 450lf - 4W500A 1350 lf $ 250.00 $ 337,500 Chiller Feeders - (3) ea 500A Disconnect Switches 3 ea $ 2,500.00 $ 7,500 Feeder to PP 1st Floor - 800A, 3Ph, 4W, 30 lf $ 325.00 $ 9,750 "***" 1 ea $ 11,250.00 $ 11,250 "***" 230 lf $ 200.00 $ 46,000 "***" 1 ea $ 4,500.00 $ 4,500 "***" 1 ea $ 3,600.00 $ 3,600 "***" 230 lf $ 200.00 $ 46,000 "***" 1 ea $ 3,600.00 $ 3,600 "***" 1 ea $ 3,600.00 $ 3,600 "***" $ — New Feeder to Ex Office Panel, 1600A -480/277V 250 lf $ 847.81 $ 211,953 New Feeder to Panel Box 2nd Floor, 1200A -480/277V 250 lf $ 496.35 $ 124,087 Feeder to Utility PP - 1200A, 480/277V 2nd Floor 200 lf $ 496.35 $ 99,270 Utility PP - 1200A, 3Ph, 4W 1 ea $ 4,500.00 $ 4,500 Feeder to 112.5KVA XFMR & 400A Pnl 50 lf $ 200.00 $ 10,000 XFMR 112.5KVA 480V - 280/120V 2 ea $ 4,500.00 $ 9,000 Feeder to 75KVA XFMR, 200A & 250A Pnl 25 lf $ 150.00 $ 3,750 XFMR 75KVA 480V - 280/120V, 200A 1 ea $ 3,600.00 $ 3,600 Equip Feeders below $ — Feeder to UPS Panel - 400A 250 lf $ 184.76 $ 46,190 UPS & Panel - 50kVA 1 ea $ 70,000 $ 70,000 "***" 1 ea $ 4,500.00 $ 4,500 "***" 150 lf $ 200.00 $ 30,000 "***" 6 ea $ 4,500.00 $ 27,000 Equip Feeders below $ — Power Feeder 60 lf $ 1,415.50 $ 84,930 Emergency Diesel Generator w/ Day Backup, 2500KW 1 ea $ 875,000.00 $ 875,000 $ 2,544,474 LIGHTING, LIGHTING CONTROL, RECEPTACLES "***" 47,874 sf $ 22.35 $ 1,069,984 Offices, Corridors & Labs Utility / 20,558 sf $ 14.90 $ 306,314 Mechanical 37,334 sf $ 11.18 $ 417,207 $ — $ 1,793,506 SPECIAL SYSTEMS $ — VFD's for CHW Pumps, 40 HP ea 2 ea $ 6,705 $ 13,410 VFD's for HHW Skid, 15 HP ea 2 ea $ 5,588 $ 11,175 Heat tracing of outdoor chilled water piping 132 lf $ 33.53 $ 4,425 Fire Alarm 105,766 sf $ 5.00 $ 528,830

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Plumbing & Fire Protection PLUMBING Instantaneous water heater - for remote located sinks 3 ea $ 1,500.00 $ 4,500 EWSS w. mixing valves 10 ea $ 6,000.00 $ 60,000 Janitor Sink 2 ea $ 1,750.00 $ 3,500 Lavatories (small sink) 15 ea $ 500.00 $ 7,500 Water Closets (toilet) 14 ea $ 5,000.00 $ 70,000 Urinals 5 ea $ 1,500.00 $ 7,500 Water Fountains 2 ea $ 1,000 $ 2,000 Sinks 7 ea $ 600.00 $ 4,200 Shower 2 ea $ 5,000.00 $ 10,000 Elevator Pit Sump Pump 1 ea $ 1,500.00 $ 1,500 Floor Drains 10 ea $ 1,000.00 $ 10,000 Point of Use Haz Waste Receptacles 2 ea $ 750 $ 1,500 PIPING MAINS DCW Main - assume 3" copper, insulated, w/ valves 670 lf $ 142.00 $ 95,140 DHW Main - assume 3" copper, insulated, w/ valves 650 lf $ 142.00 $ 92,300 Above slab sanitary waste piping 4" cast iron, no insulation/no valves 663 lf $ 130.00 $ 86,190 Under-slab sanitary waste piping 4" cast iron, no insulation/no valves 400 lf $ 130.00 $ 52,000 Sanitary Vent Piping 2" cast iron - assume 8 risers, no insulation/no v 240 lf $ 103.00 $ 24,720 LOCAL PIPING DCW Local 1.5" copper, insulated, w/ valves 1,140 lf $ 171.00 $ 194,940 DHW Local 1.5" copper, insulated, w/ valves 720 lf $ 171.00 $ 123,120 Sanitary Waste 4" cast iron, no insulation/no valves 1,200 lf $ 277.00 $ 332,400 Plumbing Permit 1 lot $ 10,000.00 $ 10,000 Plumbing Total $ 1,193,010 FIRE PROTECTION Mains 6" carbon steel 700 lf $ 150.00 $ 105,000 Pre-Action Dry Type - clean suites only 5,000 sf $ 12.00 $ 60,000 Fire Protection - Area under Mezz level 38,000 sf $ 5.00 $ 190,000 Existing Interstitial Level Minor Rework 48,266 sf $ 0.50 $ 24,133 Server / Telecom Rooms 1,734 sf $ 6.00 $ 10,404 Fire Protection - Rework Office Ordinary Hazard 20,000 sf $ 2.50 $ 50,000 Fire Protection Total $ 439,537 Plumbing & Fire Protection Total $ 1,632,547 $ 1,632,547

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Ò Architectural / Structural Walls - GWB - 1/1 on 3 5/8" Mtl Studs 26,930 sf $ 8.10 $ 218,133 Walls - GWB - Shaftwall 1hr Fire Rated on 6" Mtl Studs 4,480 sf $ 9.90 $ 44,352 Mesh Wire Walls 1,363 sf $ 3.50 $ 4,771 ADD for Fiber Rock 75,254 sf $ 0.90 $ 67,729 Blocking for Wall Guard 200 lf $ 2.25 $ 450 Rough Carpentry / Blocking 70,000 sf $ 0.25 $ 17,500 Doors & Windows 3x7 HM Door & Frame 35 ea $ 1,170.00 $ 40,950 PAIR 6x7 HM Doors & Frame 45 pr $ 1,620.00 $ 72,900 Entrance Single Glass Doors & HM Frame 2 ea $ 1,250.00 $ 2,500 Sgl Process Door & Frame 1 ea $ 5,850.00 $ 5,850 Dbl Process Steel Door & Frame 4 ea $ 12,600.00 $ 50,400 ADD For Door Interlock Prep and Device 5 ea $ 450.00 $ 2,250 Slider or Rapid Roll Fabric Door - 8' x 10' 3 ea $ 9,000.00 $ 27,000 Viewing Windows 175 sf $ 60.00 $ 10,500 Flooring Prep Existing Floor for New Covering 26,681 sf $ 1.13 $ 30,016 Entrance Mat 174 sf $ 25.00 $ 4,350 Epoxy Floor 11,888 sf $ 10.80 $ 128,390 VCT Floor 6,195 sf $ 2.57 $ 15,890 Seamless Welded Vinyl 4,056 sf $ 10.00 $ 40,560 Carpet 1,261 sy $ 27.00 $ 34,038 Polished Concrete 4,542 sf $ 8.00 $ 36,336 Sealed Concrete 58,795 sf $ 1.13 $ 66,144 Bases Epoxy Floor Coved Base 2,787 lf $ 16.20 $ 45,149 Smls Welded Cove 1,319 lf $ 14.00 $ 18,466 Vinyl Base 6,176 lf $ 2.03 $ 12,506 Ceilings Suspended Drywall Ceiling 12,353 sf $ 11.25 $ 138,971 2x4 Lay-In Mylar Gasketed Ceiling 1,005 sf $ 9.90 $ 9,950 2x4 Lay-In Ceiling 81,855 sf $ 3.47 $ 283,628 Finishes Paint Walls - latex 142,455 sf $ 0.77 $ 108,978 Paint Walls - epoxy 41,643 sf $ 1.58 $ 65,588 Epoxy Paint Gypsum Ceiling 12,353 sf $ 1.80 $ 22,235 Paint Door & Frame 87 ea $ 58.50 $ 5,090 FRP 648 sf $ 17.50 $ 11,340 Caulking Allowance 1 ls $ 15,000.00 $ 15,000 Room Accessories Toilet Partitions - Phenolic Resin 11 ea $ 1,260.00 $ 13,860 Urinal Screen 2 ea $ 500.00 $ 1,000 Toilet Accessories 1 ls $ 20,000.00 $ 20,000 12' x 15' Metal Locker, Single Tier with Sloped Top 370 ea $ 225.00 $ 83,250 Locker Room Bench 100 lf $ 54.00 $ 5,400 Fire Extinguisher and Cabinet - allow 10 ea $ 350.00 $ 3,500 $ 2,008,448 Interior Construction Total SPECIAL CONSTRUCTION Pre-Eng Structural (allow 40' x 40' x 15' avg ht) 1,600 sf $ 60.00 $ 96,000 Process Modular Clean Rooms - 8250sf @ approx. $265.94 / Sf Stainless Stl Items 1 ls $ 2,194,000 $ 2,194,000

Cost Estimate CONFIDENTIAL Order of Magnitude Estimate Building HVAC / Utilities HHW Skid - 3,000 MBH 1 ls $ 85,000.00 $ 85,000 Boilers (3), nat gas 3 ea $ 30,000.00 $ 90,000 Domestic Electric Water Heater w. expansion tank 1 ea $ 8,000.00 $ 8,000 Sump Pump for Elevator Pit 1 ls $ 1,500.00 $ 1,500 PIPING MAINS CHWs/r 8" carbon steel, w. valves and insulation 560 lf $ 275.00 $ 154,000 CHWs/r 6" carbon steel, w. valves and insulation (heat trace) w/ el 132 lf $ 225.00 $ 29,700 CHWs/r 2" carbon steel, w. valves and insulation 676 lf $ 81.00 $ 54,756 HHWs/r 2"-3" carbon steel 1,286 lf $ 115.00 $ 147,890 Outdoor HHWs/r - 2"3" carbon steel 126 lf $ 115.00 $ 14,490 Nat Gas 2" carbon steel w. valves 460 lf $ 81.00 $ 37,260 Clean Steam 1" 316L pipe, w. valves and insulation 300 lf $ 111.00 $ 33,300 LOCAL PIPING CHWs/r 2" carbon steel 240 lf $ 140.00 $ 33,600 HHWs/r 1" copper 2,600 lf $ 122.00 $ 317,200 Nat Gas 1.5" carbon steel 420 lf $ 82.00 $ 34,440 Clean Steam 1" 316L pipe to process air handlers 150 lf $ 135.00 $ 20,250 Clean Steam 1" 316L pipe to 2 part washers and 4 autoclaves 600 lf $ 135.00 $ 81,000 Refrigerant Piping for Split Systems - suction and liquid lines 540 lf $ 84.00 $ 45,360 Refrigerant Charge 1 ls $ 5,000.00 $ 5,000 Coil Fitout - large/medium 3 ea $ 6,500.00 $ 19,500 Coil Fitout - small 5 ea $ 4,500.00 $ 22,500 Humidifier section coil fitout, if required 8 ea $ 4,500.00 $ 36,000 Condensate Piping 150 lf $ 84.00 $ 12,600 Trim Piping Factored 1 ls $ 131,600.00 $ 131,600 HVAC Contractor Permit 1 ls $ 15,000.00 $ 15,000 BAS Control System 244 pts $ 1,775.00 $ 433,100 HVAC Total $ 4,877,411 $ 4,877,411

Next results

Draft better contracts
faster with AllDrafts

AllDrafts is a cloud-based editor designed specifically for contracts. With automatic formatting, a massive clause library, smart redaction, and insanely easy templates, it’s a welcome change from Word.

And AllDrafts generates clean Word and PDF files from any draft.